Net present value (NPV) explained, with a worked example

By Adam Niazi FCCA · Last updated 12 October 2026

Net present value (NPV) is the value of a project's future cash flows in today's money, after discounting at the cost of capital and subtracting the initial investment. If NPV is positive, the project adds value and should be accepted. Example: a £1,000 project returning £400, £500 and £600 at a 10% cost of capital has an NPV of £227.65.

The NPV formula and decision rule

NPV = Σ [Cash flowt ÷ (1 + r)t] − initial investment, where r is the cost of capital and t the year.

  • NPV positive: accept. The project earns more than investors require.
  • NPV zero: it earns exactly the required return (this rate is the IRR).
  • NPV negative: reject on financial grounds.

Worked example

A project costs £1,000 and returns £400, £500 and £600 over three years. The cost of capital is 10%.

YearCash flow (£)Discount factor at 10%Present value (£)
0(1,000)1.000(1,000.00)
14000.909363.64
25000.826413.22
36000.751450.79
NPV227.65

The NPV is positive, so the project should go ahead: it increases the organisation's value by about £228 in today's money.

Other investment appraisal methods

The book's Chapter 18 compares four methods. Using the same project:

MethodResult for the exampleBest forWeakness
NPV£227.65Long-term projects where the cost of capital is known; shows the effect on shareholder wealthNeeds a reliable cost of capital
IRRAbout 21.7%When the cost of capital is uncertain: shows the highest it could beCan rank projects wrongly
Payback2.17 years (£900 back after 2 years, then £100 of £600 in year 3)Short-term projects or when cash is tightIgnores cash after payback and the time value of money (unless discounted)
Accounting rate of return16.7% (average profit £166.67 after straight-line depreciation of £333.33 a year, ÷ £1,000)Comparing with profit-based targetsUses profit, not cash; can be manipulated

Good practice is to use more than one method and to consider non-financial factors too.

Advantages and limitations of NPV

Advantages

  • Uses the time value of money and all cash flows
  • Gives an absolute money figure: the value added
  • Consistent with maximising shareholder wealth

Limitations

  • Depends on forecasts and the chosen discount rate
  • Harder for non-finance managers to understand than payback
  • Ignores non-financial and strategic benefits unless added separately

NPV in ACCA SBL

You may need to interpret or challenge NPV figures in an exhibit. Ask: are the cash flow forecasts realistic? Is the discount rate right for the risk? What happens if sales are 10% lower (sensitivity)? Then weigh the result against strategic fit and stakeholder impact before recommending.

FAQs

What is NPV?

Net present value is the present value of a project's future cash inflows minus the present value of its outflows, discounted at the cost of capital. A positive NPV means the project adds value.

What is the NPV formula?

NPV = sum of [cash flow in year t ÷ (1 + r) to the power t] minus the initial investment, where r is the cost of capital.

Is a negative NPV bad?

Yes, financially: the project returns less than the cost of capital and would reduce shareholder wealth. It may still be chosen for strategic, legal or ethical reasons, which should be stated.

What is the Excel NPV trap?

Excel's =NPV function assumes the first cash flow is at the end of year 1. Leave the year 0 investment out of the range and add it separately: =NPV(rate, year1:yearN) + year0.

NPV vs IRR: which is better?

NPV, because it measures the money value added at the actual cost of capital. IRR is a useful percentage but can rank projects wrongly.